Just the Two of Us

Just the Two of Us

After 35+ years of marriage, two wonderful sons, living and working in Australia, Sweden, UK and USA we are now 'just the two of us' plus a very spoilt Shitzu.

Following five years at The Sandhurst Club it is time to downsize. Our criteria - build a new home in a development within ten minutes of John's Sandhurst Golf Club, access to Monash and Eastlink Freeways, all new infrastructure and proposed services, recycled water and no Management Company or Body Corporate Fees.

We invite you to view our journey as we build with Carlisle Homes our 'Savannah 28' at 'The Avenue at Casey', a masterplanned community meeting all our criteria.

Monday, November 15, 2010

ROOF TILES

Roof tiles in one day - ridge capping yet to be fitted.

 

Saturday, November 13, 2010

FASCIAS AND GUTTERS - Carlisle Walkthru

Met our SS this morning for a walkthru and progress update.  All proceeding as scheduled with fascias and gutters being installed in the pouring rain. Roof tiled next week and lockup before Xmas.

 

Friday, November 12, 2010

Carlisle Homes Update

Spoke to SS - due to roof being tiled Monday and Tuesday we rescheduled our walkthru meeting to tomorrow morning 8.00 a.m.

Tuesday, November 9, 2010

FRAME COMPLETED - WINDOWS INSTALLED

Frame completed - awaiting inspection. Windows installed and roof tiles delivered. Site Supervisor 'Gary' called to introduce himself - arranged an introduction meeting and walkthru inspection for next Tuesday. Gutters and fascias to be installed before roof tiling next week.  Also, met our back neighbours - waiting on imminent Title of land to begin construction.  SE Water moved our meters and taps, now we don't see them from inside the front door. Site and house clean - excellent job.

Master Bedroom Windows

C'mon In
Great tradesmen - look how clean they left it

Sunday, November 7, 2010

Frame Resumes and Roof Trusses

Framers returned Saturday although there is still timber missing?  The Estate was a hive of activity on Saturday, tradesmen everywhere.


       
    

Wednesday, November 3, 2010

Frame Holdup

Frame not completed.....timber stolen!!!  Replacement timber required before trusses can be delivered and erected. Contacted SE Water to enquire moving water meters and taps; 600mm left or right only - $132 before plumber connects to house. Oak Tree planting continues along Mountain View Boulevarde.